View Single Post
Yes this might have been hinted at before but if anyone can point me to any discussion on this I would be grateful or just tell me what I am doing wrong.

SCENARIO:
You have a Sequential Project with 3 actions each set to repeat monthly.
Action one is on the 1st
Action two is on the 7th
Action three is on the 20th

You complete action one on the 1st.
A new action is automatically created for the 1st of the next month but it is inserted between the original and the Action set for the 7th.

On clean up it is still in its original place.
Because of that it becomes the NEXT ACTION rather than Action two going to the head of the queue. (When you create a new action by the "New Action Button" It does indeed go to the bottom of the list.)

Yes you can move actions up and down by u and d but surely this putting a new action in the correct place AUTOMATICALLY should be a priority.

Sorting in context view DOES place actions in there correct place "Due Tomorrow" "Due within that next week" etc but that sorting will not put Action 2 in the correct time slot in context view because it is not considered to be the next action!


I have been using iGTD for sometime and this was an issue there which was fixed. The new iGTD2 is for Lepoard only and is of no use to me as I have a lot of Apps that would need upgrading before I could go to system 10.5.

Sorry if this is a repeat of an already existing thread but I couldn't find an explanation like the one I have given above in my searches by using the term "sequential" or "repeating".

Last edited by Sandpiper; 2008-01-02 at 01:16 PM..