In Omnifocus 2 for iphone, When I try to change the Defer or Due Date of an existing task, the information inside the action shows one set of dates. When you view the task in a Project or in Forecast, the original due dates are shown.

How do I get the modified dates to be visible within Forecast or Project views?

Also, these errors synced over to my iPad Omnifocus 1 and now those items do not show up in the correct forecast locations.

I tried deleting the dates completely from both applications, but it still shows up as being due at the original date.

My data is getting really messed up now.