View Single Post
Hi whpalmer4,

That did answer the question - thanks. Previously Omniplan wasn't allowing me to do this; it kept on moving the durations around, even though the 'Keep effort and Duraction fixed' was selected. Seems to work OK now, although I still have to remember the original duration to return to once I've added the 100% resources.