Leveling in OmniPlan should not overload anywhere unless the schedule is impossible. For example, 3 weeks of work with a locked end date 2 weeks from now will create an overloaded schedule.

I'd be really curious to take a look at your file and see what's gone awry. Could you please send a copy of your file to us? The "Send Feedback" option in OmniPlan's help menu can generate an anonymous version of your file (task names, resources, notes changed to nonsense) and email it to us.

Thanks in advance for your help.
--
Liz