View Single Post
Right, but assign a resource. Then change the hours of work per day. My point is that the Duration column in the WBS should be the same as the length of the activity bar in the Gantt. My exp was giving me a change in the duration column after changing the work hours per day, but not changing the gantt bar (resource is assigned to activity and custom schedule is already set)