This isn't too hard to arrange, especially if you have milestones for the completion of each section of the work. Just put a milestone out past the actual end of the project via a F-S dependency and a long lead time, and hook that up to the end of any earlier phase for which you want to see a critical path. Remove the dependency when you want to see the overall project's critical path as normal.