I have been doing this manually to some extent, playing around with the % for assignment. One thing I noticed is that if you manually change the duration, it assumes you want to change the effort accordingly but keep the assignments the same.

One potential solution would be to allow that behaviour to change, so that you could set the duration and effort, and it would proportionally alter the assignments for the committed resources.

It would be nice to be able to assign specific hours to individual resources, though.