View Single Post
Quote:
Originally Posted by adelheid View Post
When I print a report of a project, the overal percentage completed is shown. This overall percentage however is not visible in OmniPlan.

I have now added a task, under which I group all other tasks, to be able to see that percentage without having to print a report.

Is there another way to be able to see that percentage, i.e. without creating that extra task?
If you click on the text along the bottom of OmniPlan window, it'll cycle thru different project totals like percentage complete, project costs so far, etc...