Originally Posted by Brian View Post

(Slightly more OmniPlan-specifically: you should be able to model the dependencies between the processes just fine. Once you have the processes set up, your interactions with the processes would just be tasks that have you assigned as one of the resources required to complete them.)
One scenario I wasn't sure how to handle via OmniPlan was the possibility that process A might have some event that happens after X units of time, process B has some event that happens after Y units of time, and those two events need to be synchronized to happen at the same time. Or even simpler, how to set a constraint relative to some other event (for example, this task must start no earlier than 5 hours and no later than 7 hours after milestone XYZ)—lead times can be used for the no earlier part, but how to do the no later part without being forced to put in absolute dates/times?