Member
2007-01-16, 12:02 AM
Normally, when I start writing a plan, I put some rough durations in for all tasks and only then start assigning resources to them. OP seems to fix Effort and recalculate Duration by default, which means if I don't assign exactly one resource to a task things go horribly wrong.
Is there an option to set the default for all new tasks. Of course it's not difficult to select all and change their setting, but I always end up adding a new task and forgetting to change it...