View Single Post
Hi Everyone,

I have a project that has multiple recurring tasks. For some reason that I cannot figure out, some tasks are duplicating. Same month and date.

Each task is set to recur once a month on a set date. I've also noticed that some tasks are showing up in the project before the previous task has been completed.

For example, I have an AMEX bill due on the 8th of each month. The task for Oct 8 is displaying as it should be so is the Nov 8th task. I'm using the Availability Filter set to Remaining. This was working in the past but rather than rebuild the project, I'd like to see if the issue exists between the chair and the keyboard or if anyone else is seeing this...

It's happening on my iPad as well..


Last edited by bmushrush; 2012-09-21 at 10:10 AM.. Reason: Attach Screenshot