Hi,

I need to produce a custom extract of the plan to feed into another system. The best way seems to be to write an applescript that can read through every task in a project and extract only the ones that I have tagged with a custom field (TaskType) value of "E" into a text file.

Unfortunately I don't know applescript. Are there any script examples doing this, or something very similar that would show me how to achieve this?

I also need to extract the information that shows up on the status bar of OmniPlan (overall % complete, project start, project end, duration and effort).