View Single Post
If the projects are completely independent, you can track them in separate files. However, if people work on multiple projects at once, the project leveling won't properly account for work on another project. In that case, your best option is to put each project as a top-level group in OmniPlan. As you noted, this has limitations. We want a better way to share resources across projects.