Thanks for the reply.

When I use MPX, MS Project appears not to properly capture details of resource's work schedules. Planned Start/End dates appear correct, but these details do not seem to be represented somehow.

Is this a known issue?

I will work on a sanitized plan that does not include proprietary information but still displays the import issue in MS Proj 2003 via MS Proj XML format.