View Single Post
Quote:
Originally Posted by sbjordal View Post
That works for now, although, there was no-way to know where to click. That's not very good UI design ;)

Can we get a feature request in to get static total for effort and duration somewhere in the task list without having to group the tasks?

If you have a project with potentially 70-80 tasks, all tasks appear are a part of the first task group.
We do want to make project status info at the bottom of the window easier to find in later versions of OmniPlan. What if OmniPlan remembered what was displayed in the status area during a save? That way, you could just click to show the total effort and duration once and every time you reopened the file after a save it would still display the total.