Originally Posted by Mukiwa View Post
I've then gone to the working time and changed them to reflect my company working hours: 09:30 - 12:30 and 13:30 - 18:00. Those working hours multiplied by the rate set in the resources inspector should equal our charge out day rate. All good so far.
With your working hours, your company's normal work day is 7.5 hours a day. You will probably need to change the effort conversion factors in the "Project : Formatting" inspector to reflect this because the default setting is 8 hours.