Quote:
Originally Posted by Mukiwa
I've then gone to the working time and changed them to reflect my company working hours: 09:30 - 12:30 and 13:30 - 18:00. Those working hours multiplied by the rate set in the resources inspector should equal our charge out day rate. All good so far.
|
With your working hours, your company's normal work day is 7.5 hours a day. You will probably need to change the effort conversion factors in the "Project : Formatting" inspector to reflect this because the default setting is 8 hours.