To create a dependency the other way, you can hover your cursor over a task bar in the gantt chart until you see two arrowheads show up. Click and drag the arrowhead from one end of the task to the other end of the task above it.

For example, to set up a S->S dependency from task 2 to task 1, drag an arrowhead from the beginning of task 2 to the beginning of task 1.