View Single Post
FIrst, I agree that it would be incredibly useful to be able to reorganize tasks in a perspective like "Today". But, a workaround that I learned from David Sparks is to use the Start Date to set a specific time to do each task. If you have 500 tasks, there is NO WAY you are going to touch all 500 much less complete anything. So, you select the X number of tasks (10?) that you want to accomplish today and set a Start Time for each. In the sort field, use "start time" and in the availability field you use "Available". A task that is scheduled for 8a will sort before the one at 9a, etc. If the current time is 10a, only the tasks you want to work on prior to 10a will show on your list. They will only appear as the time encompasses them.

No idea if this helps or is unique to this thread. But, it is the workaround I use. Thanks to David Sparks.

My vote is still to providethe ability to reorganize the tasks as the user wants. Grouping and sort just need to be turned off in the perspective.