Very new to this, just purchased OmniPlan for a project that requires more than the Excel spreadsheet I would normally use...

So in entering the 100+ tasks I entered everything as "actual" when they should be "baseline"

What is the best way of deleting all the "actual" dates and changing them to "baseline" dates without redoing the whole thing?

*Is* there an easy way? Or do I chalk this up to "dumb" and start again?

Thanks for any assistance

Grant