Thanks for the tip on lead times. They do seem to work *almost* as I was hoping... :)

The problem I'm having is: I've edited the resource availability so that there's basically a 14 day gap where no resources will be available, but I'd like the "wait time" to still function without taking that into account. In other words, if I'm waiting for something from someone else, it doesn't matter if I don't have any resources to work on a task... Is that possible using lead times?

When I try it on my particular plan, the lead time pads out 14 days, but not 14 calendar days, but instead 14 "resource" available days...

And thanks for the heads up on 2w vs. 14d... I'm sure that would have bit me at some point. ;)