Originally Posted by shoimthewoim View Post
I, too, would value a more efficient way to track performance of a project by entering actual hours logged to a project. I use OP for scheduling my project which includes staff from several different divisions in my organisation. Each month our corporate system provides me with a report of the effort logged by each staff member to date in hh:mm (no days).
There is no direct way to do this in the UI -- dragging the sliders (or typing percentages in the inspector) is the most direct approach. If your corporate system provides a relatively simple text file containing staff names, task names and hours/minutes worked on each task, it would be quite straight-forward to automate the entire process of updating progress with an applescript.