Hi there,

Really simple question, when I come to print out my plan, is there a way to show the start and end dates of each task?

Due to the size of the project, the date range bar at the top condenses and makes the actual dates unreadable.

Selecting a different view is not an option as I need to show the specific day an task will be completed.

Thanks