If I'm understanding the question correctly, you want to display durations in a format like "2w 3d 4h"? Yes, this is quite possible. You can turn units off and on in one of the Project inspectors. I think it's called "Units"? There's also the concept of "effort conversion factors" to be aware of, also configurable. For example, by default 1 week of effort is 5 days, not 7. I'm out of the office on an iPad or I'd point you to the UI a little more specifically, but I think this will get you there.

Tom