View Single Post
An addition to my previous post: when I say the task will span so many days, i mean so many project working days. If the project work schedule also is only M 9-3 and Th 9-12, then the 8 hour task starting Monday 9am will only span 2 days in the chart unless you've selected the option to show off hours (View->Gantt chart->Show Off-hours)