Quote:
Originally Posted by fabienne
Hi
I cannot find the Applescript. If the link changed, would you please post it again?
Thank you.
|
This script is no longer required. Now, you can simply select all the tasks in one project plan and copy/paste it into another project plan to merge the two. As long as you have named all of your resources identically in both projects (Bob in project 1 and project 2, not Bob in project 1 and Bobby in project 2) you won't accidentally double-up on resources after the merge.