Quote:
Originally Posted by vil
Hi everyone,
So, I've set the unit %s for each of my staff and assigned tasks to them; I've then gone and changed the unit %s for the staff, but each task still records the original % value. What I have now is a lot of tasks where Fred Bloggs is assigned at "50% of 70%" instead of "70% of 70%".
Is there an easy way to update all of these to the maximum % value for the staff member?
|
You can select all the tasks that need to be changed by holding the CMD key while clicking on each task. Once they're highlighted, bring up the "Task : Information" inspector and you'll be able to type in "70% of 70%" to apply it to all your highlighted tasks.