1. Complete tasks get rescheduled / releveled. When I have flagged a task as 100% complete, I don't want it to change in anyway. However, if I make changes to, say the availability of a resource, OP will reschedule the completed task and calculated a new end date. Am I missing anything here?
Could you send in the project files that show this behavior? I'd like to observe this behavior directly and write up a bug report. You can email it omniplan@omnigroup.com.

Quote:
2. Split tasks. OP currenly defers the start of a task if there is a resource overload. I would like it to split the task and delay the completion date but leave the start date where it is.
There isn't a way to split the task that way in OmniPlan right now. The only workaround you could do would be to create two tasks for Task A and call them "part 1" and "part 2". Not a very elegant solution I know.

We have a feature request for split tasks in our database so I'll add a vote to it for you. :)