I'm trying to understand the finer points of task splitting.

I can provoke a task to be split by levelling two overlapping tasks with splitting enabled and where the second is smaller and immovable.

If I move or remove the second task and re-level, the split task re-assembles itself.

But if just I re-level with splitting disabled, the split task stays split.

Is there an elegant way to re-join split tasks without temporarily removing the cause of the splitting?