Guys, anyone?
What I can see is that splitting a task with two resources assigned to it is not giving me flexibility to assign first half of the split task to resource 1 and the second one to resource 2. If I want resource 2 to work on something else while resource 1 does the first half of the split task and resource 1 working on something else when resource 2 starts on the second half, it prevents leveling from doing fine job.
Meanwhile a group with two tasks in it, works out just fine.
I was wondering in which case split task is better than a group. I see people were asking for split task feature to be added, but maybe they don't assign a split task to more than one resource and it works fine then?
Am I having a special case or asking a weird question? :-)