Originally Posted by whpalmer4 View Post
Sure! Select the milestone, open the Task inspector (cmd-1), set the date for the milestone. If you connect up the rest of the dependency graph to the milestone, you'll get a violation if the prerequisites aren't going to finish before the milestone starts. You can also put a constraint on the milestone via the same mechanism if there is some flexibility.
so for a milestone that has to be done "1 year from the start of the project", where do I put the date in the inspector - do I set the start date as the start of the project, or just the 1 year-in date as the end date, or make them identical?

thanks,