View Single Post
Quote:
Originally Posted by akwong View Post
There isn't a way to split the task that way in OmniPlan right now. The only workaround you could do would be to create two tasks for Task A and call them "part 1" and "part 2". Not a very elegant solution I know.
Did a "Split Task" feature ever get added? It's been almost two years now.