I'm not entirely sure I'm understanding your request, but I'll describe what I think you are asking for, and how you could do it with the existing product.

You've got two projects, one for Acme Widgets and one for Zenith Observatory. You've got a couple of staff people, Stan and Ollie, who work Monday and Tuesday on Acme work, and Wednesday through Friday on Zenith work, plus Curly, who works all five days per week on Zenith work. I would set up separate Stan and Ollie resources for the two projects, with Stan (Acme) working Mon-Tue, Stan (Zenith) working Wed-Fri, Ollie (Acme) Mon-Tue, Ollie (Zenith) Wed-Fri. Then I assign the resources to the tasks as appropriate, and level. The Gantt chart may show bars extending over days where the resources do not work, but that is normal and if examined closely, you'll see that the overlap of the bars with days where the resources are active accounts for exactly the right amount of effort. I've attached a simple example.