You could create a 2 hour long task and set a start and end date constraint in the "Task : Information" inspector. This allows you to note that the task will only take 2 hours, but it can be done within that 3 day time frame. If the task actually takes 1 day instead of 2 hours, you would just adjust the effort value to 1 day.