Im new to this tool. I need to put in a - start date or rather I want to begin a task based upon the forecast completion of another and if that task slips, I want my second one to do so as well.

In MS Proj, I could link a task with a - sign in the start date and it would adjust the days automatically, I can't seem to find that function. I would appreciate hints to do this.

Thanks,

Hugh