View Single Post
Thank you for the response Ken.

How does the assumption that the due date is the most important,
fit in with the paradigm of how the available filter works?
If a task has a start date of today
a due date of tomorrow
it shows up in the available filter

when I complete it...
it shows up in the available filter.
when I complete it again
it shows up in the available filter.

From my perspective...
the action should no longer be available
because I completed it.

What about changing the logic so that...
if the item has a start date and a due date
and the current date is included or is in-between or after the due date
the repeat interval is applied to the start date
and the due date is calculated based on the start date

Can you think of any examples where this would cause a problem?