Hi! If I understand correctly, you want your exported OmniPlan events to be split into separate iCal events (if they are longer than one work period).
You can do this by exporting "As: One per work period" in the export sheet. This way, with the default settings in a new project, a two day task will create four iCal events: Day 1 Morning & Afternoon, Day 2 Morning & Afternoon.
Hope this answers your question!