Originally Posted by Hawkcode
Not exactly,

If I create a task and it's at the end of a Project, and give it today for a task and no other tasks in project have a due date, I would think that switching to the context view should then force that task to top.

Even if I try and sort by that it doesn't show up. The project is set up to do one task at time. I think it should show what's due, don't you?
Briefly, a one-task-at-a-time project is considered to be sequential. That is, each task is dependent on the one before it. If that isn't the case, then you should be using a parallel project, or some combination of nested subprojects.
__________________
Cheers,