Hello everyone. I'm half experienced with project management concepts, and
I'm in trouble trying to figure out the right way to put this cenario in my project plan:
The case is like this:
I have 2 tasks:
1.1 - Search for image references
1.2 - Keywording* of the selected images
The issue is that "1.1" is a 8h task, that happens weekly, and "1.2" is a 2h task that has to be done every time "1.1" is completed.
As I know, 1.1 can be called a recurring task and 1.2 is dependent from 1.1.
How can I represent this in my plan?
thanks for help!
------------------------------------