View Single Post
Hello,

I am trailing OmniPlan and have been trying to find the answer to this to no avail - hope you can help :).

I would like to specify task lengths in full months. When I do that (in the effort column), and switch the header to months, tasks end earlier than the end of the month they should end in. Of course I can adjust the task length to end at the end of the month, but then the effort is no longer right.

On a related note, is it possible to have month count instead of T, T+1 etc in the header? I would like 1, 2, 3 etc.

Thanks!

Cheers /Christian