Did you set "Normal Work Day" to include weekends for the resources only? I assume you adjusted the "Normal Work Day" for each of the resources, but not for the project itself. Make sure you deselect everything and adjust the "Normal Work Day" for the entire project. This will allow setting tasks to begin on days you choose, such as weekends.

This is how I make that change and I hope it works for you.