Originally Posted by mcroasmun
This is the behavior I expect, but instead I find that changing resources assigned changes the duration against a fixed effort value, regardless of which icon is darkened. Is that not what you get? I find this behavior even in a brand new document.
This is precisely the experiment I performed:
1) Open a new project and create a task and set it to "track task by duration."
2) Create a new resource who works 20 hrs/wk
3) Assign the resource to the task and observe that effort remains 1w but duration increases to 2w. This should not be.