Hi All,

Apologies if this has been answered already elsewhere. Is there a way to set a task dependency (or, more appropriately, constraint) whereby a task cannot start until a preceding task reaches X% completion?

Essentially I have a situation where I have task2 dependent upon task1 (theoretically), however work may actually commence on task2 provided that task1 has reached a minimum of 75% completion. Needless to say, task 2 cannot end prior to task1 completion, of course.

Is there a way to do this?

Thanks in advance,


Leland