Cool:
I like it. the icon is pretty good and the feedback is ideal. However, this still does not answer my questions. What is I have two tasks assigned to the same resource. I usually do a dependency (leveling dependency) between them. in OmniPlan, all I can do is press the auto-level button. but I want to do a Manual Leveling.
I tried adding predecessor in the task inspecto but it was greyed out due to not being in the gant chart view.
Any ideas ?