Also the fact that I must mark it as complete, rather than just having it be complete after all the tasks have been checked off. This is a big waste of time.
Projects often aren't fully planned out into actions before they are started. Instead, a project often (usually) serves as a stake in the ground that marks your goal. In your review, if you can say that you've satisfied the desired outcome of the project, it is complete, but often it will remind you of some extra steps you need to take.

If we were to mark the Project implicitly completed when it had zero incomplete actions, people would lose track of their remaining work.

On feature that isn't in yet that will make this easier is that when you have a project row selected, space should mark it completed, <bug://bugs/43349> (Hitting space with a project selected should mark it complete if it is active).