I have done one task group for every customer with project opened. This allow me to handle correctly resource usage and timeline.
Right now i have two problems:
a) the auto level function does not care about project duration; in order to optimize tasks it move resource between them. The result is that you have a super-optimized time table with bug overall project duration
b) i found the filter options in the export but it does not allow to select groups

Thanks
nat