View Single Post
I would like to back date a project, because I have a project already in flight that I want to bring under Omni Plan control.

I have tried removing the start constraint on all tasks, tried adjusting the project start date, and have tried marking everything as complete. However none of these solutions seem to work.

Looking for an override here.

thanks to all. Great application, by the way.