Have you tried setting a start date, then set the repeating interval to whatever it is you want, and set the project to repeat from Completed date?
Example:
Project Test
click on start date and set to today
click on the inspector icon to view the inspector for the project
set it to repeat every 2 weeks
set it to repeat based on completion date
complete the project.
The next start date should be 12-14-2008.