View Single Post
Quote:
Originally Posted by bnz View Post
Yeah, I could create a repeating task so that I could work on it every day, but then the due date is on daily basis, there would be no "final" due date or "repeat until". Also, the repetition is kind of faulty. The next repetition is only created when the last one is checked. If I now use the forecast view, it doesn't display the repeated task on all days where I would have to work on it, but just the first one. It kind of hides the work that you have to do.
That's only one way to do it. If it is important to see the future work, instead of making a daily repeater, you make a set of 5 or 7 that each repeat weekly, or 10 or 14 that repeat bi-weekly, or whatever.

As for knowing when to stop, put in an action with a start date that tells you it's time to get rid of that repeating action...