Your assumption was right. I entered the tasks (175 of them), assigned the resources, and then changed the resource availability numbers.

The proposed fix will do the trick, but it doesn't really help, because I have to reassign the 175 tasks. I need to "rethink" and "redo" the decisions I spent a better part of an afternoon completing.

To say it a different way, I don't understand why OmniPlan doesn't allow me to change a resource availability after it has been assigned. That stuff happens all the time in real life! A developer may be available full time for a while, then something changes and now he is only available half time. I'd like OmniPlan to to say "OK then, that will kick out your ship date by 4 weeks".