I'm impressed that I was able to pretty much pick up the Beta and go with it, despite having only passing familiarity with project management software.

I also see and appreciate the parallels with OmniOutliner.

Problem 1.
I set up a project with 40+ tasks & subtasks, complete with their duration and connections. I set up 15 staff resources, just names & no details. I can allocate resources to the first couple of tasks. Then the end date of any further tasks jumps out to sometime in 2074.

This change in end date can't be fixed, either by changing the end date in the outline, or by changing the duration.

Generally though, it seems stable enough until resources are actually allocated.

Problem 2.
In the calendar view there is a one day discrepancy between the month as shown and the working week as shown. EG: the month shows 01 Jan 2007 as a Monday, the week shows 01 Jan 2007 as a Tuesday.

Problem 3.
I can't find a way to show a mid-week day as a non-working day.

Looking forward to the next beta!